1850.103-670 Implementation of the Contract Adjustment Board's decision.

1850.103-670 Implementation of the Contract Adjustment Board's decision.

(a) The contracting officer shall take action authorized in the CAB's decision.

(b) Immediately upon execution, including any required Headquarters approval, of a contract or contract modification or amendment implementing the CAB decision, the contracting officer shall forward a copy of the contractual document to the Associate General Counsel for Contracts and Procurement Law.

[76 FR 72328, Nov. 23, 2011, as amended at 80 FR 36722, June 26, 2015]